Exide Industries Cuts Ulric Renewables Stake to 26.07% After Wind Project Delay

Veena Lathe - 0 min read

Last Updated: 18th November 2026 - 03:28 pm

Key Takeaways

  • Exide Industries has diluted its holding in Ulric Renewables from 39.08% to 26.07% after a Maharashtra wind project missed its scheduled commissioning date.
  • The affected captive wind project at Jath, Maharashtra, has a contracted capacity of 10.5 MW and was intended to supply Exide's factories in the state.
  • A separate 8.4 MW wind project supplying Exide's Hosur facility in Tamil Nadu remains operational.

A delayed 10.5 MW captive wind project at Jath in Maharashtra has led Exide Industries to reduce its shareholding in renewable energy special purpose vehicle Ulric Renewables Private Limited.

Exide disclosed on November 18 that its holding in Ulric has been diluted from 39.08% to 26.07% under mutually agreed terms between Exide, Ulric and Cleantech Solar India OA 2 Pte. Ltd.

The adjustment follows the failure of the Jath project to achieve commissioning within its scheduled commencement timeline.

Why Exide Industries Reduced Its Ulric Renewables Stake

Exide originally disclosed its 39.08% investment in Ulric in April 2023.

Ulric was set up as a special purpose vehicle by Cleantech Solar India OA 2 for captive wind projects with an aggregate contracted capacity of 18.9 MW. The electricity was intended for Exide manufacturing facilities in Maharashtra and Tamil Nadu.

The portfolio covered two separate operating locations.

The 10.5 MW Jath project was meant to supply renewable electricity to Exide's Maharashtra factories. That project was not commissioned by its scheduled date.

Following the delay, the three parties executed amendment and settlement documentation. As part of those mutually agreed arrangements, Exide's ownership in Ulric was reduced by 13.01 percentage points to 26.07%.

The company did not disclose a transaction value or separate financial consideration in its November 18 filing.

Hosur Wind Project Continues to Operate

The change does not mean Exide has exited the captive wind arrangement entirely.

Ulric's 8.4 MW wind project supplying Exide's Hosur facility in Tamil Nadu remains operational, and the company said electricity supply to the plant will continue under the existing arrangement.

This distinction is important because the stake reduction relates to the settlement following the delayed Maharashtra project, while the Tamil Nadu captive wind supply continues.

Exide also stated that the transaction is not a related-party transaction. None of its promoters, promoter group entities or group companies has an interest in the transaction.

The November disclosure therefore represents a restructuring of Exide's participation in the Ulric Renewables SPV rather than a complete divestment from the captive wind power arrangement.

FREE Trading & Demat Account
Open FREE Demat Account with endless opportunities.
  • Flat ₹20 Brokerage
  • Next-gen Trading
  • Advanced Charting
  • Actionable Ideas
+91
''
By proceeding, you agree to our T&Cs*
Mobile No. belongs to
OR
hero_form

Disclaimer: Investment in securities market are subject to market risks, read all the related documents carefully before investing. For detailed disclaimer please Click here.

Open Free Demat Account

Be a part of 5paisa community - The first listed discount broker of India.

+91

By proceeding, you agree to all T&C*

footer_form